Same district, same year — promised date, physical %, booked %, complaints, last QPR. As filed. Not a ranking.

Snapshot 12 Oct 2026. Check rera.kerala.gov.in.

Ernakulam · 2024 · K-RERA/PRJ/ERN/147/2024

Ernakulam · 2024 · K-RERA/PRJ/ERN/019/2024

Same cohort: Ernakulam · 2024.

As filed
ORCHARDOn Track
Project
ORCHARD
KUNNATHUNAD, Ernakulam
Kalyan A Different Story
ELAMKULAM, Ernakulam
Promised date
23 Feb 2028
no date change on file
24 Jul 2028
no date change on file
Physical %
0%
filed 23 Oct 2023
26%
not filed
Booked %
0%
0 of 32
60%
15 of 25
Complaints
none on file
from the public complaints list
none on file
from the public complaints list
Last QPR
never filed
no quarterly update on file
Q2 2026
filed 06 Oct 2026 · -33d ago · Current

Dash means missing on the snapshot. Status is derived from filed dates. Check rera.kerala.gov.in.