Same district, same year — promised date, physical %, booked %, complaints, last QPR. As filed. Not a ranking.
Snapshot 12 Oct 2026. Check rera.kerala.gov.in.
Ernakulam · 2023 · K-RERA/PRJ/ERN/167/2023
Ernakulam · 2023 · K-RERA/PRJ/ERN/049/2023
Same cohort: Ernakulam · 2023.
Project
PRIME MERIDIAN REEF
EDAKOCHI, Ernakulam
GALAXY OXTON
ELAMKULAM, Ernakulam
Promised date
17 Dec 2028
no date change on file
29 May 2020
no date change on file
Physical %
64%
filed 11 Oct 2023
100%
not filed
Booked %
80%
16 of 20
97%
70 of 72
Complaints
none on file
from the public complaints list
6
4 final orders
Last QPR
Q2 2026
filed 01 Oct 2026 · -28d ago · Current
N/A
closed on the register — QPR not expected
Dash means missing on the snapshot. Status is derived from filed dates. Check rera.kerala.gov.in.