Same district, same year — promised date, physical %, booked %, complaints, last QPR. As filed. Not a ranking.
Snapshot 12 Oct 2026. Check rera.kerala.gov.in.
Ernakulam · 2023 · K-RERA/PRJ/ERN/166/2023
Ernakulam · 2023 · K-RERA/PRJ/ERN/022/2023
Same cohort: Ernakulam · 2023.
Project
SPARKLE SCAPES
EDAPPALLY SOUTH, Ernakulam
NATIONAL TREEDOM PARK TOWER 2
NADAMA, Ernakulam
Promised date
22 Dec 2017
no date change on file
30 Nov 2026
no date change on file
Physical %
—
not filed
100%
filed 23 Jan 2023
Booked %
100%
15 of 15
76%
26 of 34
Complaints
none on file
legal case marked on register
none on file
from the public complaints list
Last QPR
N/A
closed on the register — QPR not expected
N/A
closed on the register — QPR not expected
Dash means missing on the snapshot. Status is derived from filed dates. Check rera.kerala.gov.in.