← Projects
Compare
Same district, same year — promised date, physical %, booked %, complaints, last QPR. As filed. Not a ranking.
Snapshot 12 Oct 2026. Check rera.kerala.gov.in.
Ernakulam · 2025 · K-RERA/PRJ/ERN/134/2025
Ernakulam · 2025 · K-RERA/PRJ/ERN/006/2025
Same cohort: Ernakulam · 2025.
Project
Fern Silver Springs
KEEZHMAD, Ernakulam
HEAVEN HONOUR
EDAPPALLY SOUTH, Ernakulam
Promised date
08 Apr 2021
no date change on file
29 Feb 2028
no date change on file
Physical %
—
not filed
0%
not filed
Booked %
44%
36 of 81
0%
0 of 7
Complaints
flag on register
from the public complaints list
none on file
from the public complaints list
Last QPR
N/A
closed on the register — QPR not expected
Q4 2025
filed 07 Apr 2026 · 149d ago · Stale
Dash means missing on the snapshot. Status is derived from filed dates. Check rera.kerala.gov.in.