Same district, same year — promised date, physical %, booked %, complaints, last QPR. As filed. Not a ranking.

Snapshot 12 Oct 2026. Check rera.kerala.gov.in.

Ernakulam · 2023 · K-RERA/PRJ/ERN/119/2023

Ernakulam · 2023 · K-RERA/PRJ/ERN/078/2023

Same cohort: Ernakulam · 2023.

As filed
Project
ISLAND VALLEY
KUNNATHUNAD, Ernakulam
SPICE VALLEY
KUNNATHUNAD, Ernakulam
Promised date
30 Oct 2027
no date change on file
25 Dec 2025
8 months past promised date
Physical %
90%
not filed
82%
not filed
Booked %
60%
6 of 10
93%
13 of 14
Complaints
1
no final order on file
none on file
from the public complaints list
Last QPR
Q2 2026
filed 05 Oct 2026 · -32d ago · Current
Q2 2025
filed 07 Oct 2025 · 331d ago · Stale

Dash means missing on the snapshot. Status is derived from filed dates. Check rera.kerala.gov.in.