Same district, same year — promised date, physical %, booked %, complaints, last QPR. As filed. Not a ranking.

Snapshot 12 Oct 2026. Check rera.kerala.gov.in.

Thrissur · 2023 · K-RERA/PRJ/TSR/118/2023

Thrissur · 2023 · K-RERA/PRJ/TSR/107/2023

Same cohort: Thrissur · 2023.

As filed
TBPL ARCADECompleted
Project
TBPL ARCADE
THRISSUR, Thrissur
SANROYAL SUKRITI
CHITTILAPPILLY, Thrissur
Promised date
26 Oct 2022
no date change on file
02 Jul 2023
no date change on file
Physical %
100%
not filed
100%
not filed
Booked %
50%
7 of 14
100%
30 of 30
Complaints
none on file
from the public complaints list
none on file
legal case marked on register
Last QPR
N/A
closed on the register — QPR not expected
N/A
closed on the register — QPR not expected

Dash means missing on the snapshot. Status is derived from filed dates. Check rera.kerala.gov.in.