Same district, same year — promised date, physical %, booked %, complaints, last QPR. As filed. Not a ranking.

Snapshot 12 Oct 2026. Check rera.kerala.gov.in.

Ernakulam · 2023 · K-RERA/PRJ/ERN/085/2023

Ernakulam · 2023 · K-RERA/PRJ/ERN/103/2023

Same cohort: Ernakulam · 2023.

As filed
Project
SIDDHI CHANDRAVILASAM
NADAMA, Ernakulam
VARMA CRYSTAL
NADAMA, Ernakulam
Promised date
01 Jul 2028
no date change on file
28 Feb 2029
no date change on file
Physical %
99%
filed 11 Oct 2023
78%
filed 04 Dec 2023
Booked %
61%
14 of 23
97%
31 of 32
Complaints
none on file
from the public complaints list
none on file
from the public complaints list
Last QPR
Q1 2026
filed 07 Jul 2026 · 58d ago · Current
Q2 2026
filed 07 Oct 2026 · -34d ago · Current

Dash means missing on the snapshot. Status is derived from filed dates. Check rera.kerala.gov.in.