Same district, same year — promised date, physical %, booked %, complaints, last QPR. As filed. Not a ranking.

Snapshot 12 Oct 2026. Check rera.kerala.gov.in.

Thrissur · 2023 · K-RERA/PRJ/TSR/058/2023

Thrissur · 2023 · K-RERA/PRJ/TSR/054/2023

Same cohort: Thrissur · 2023.

As filed
Project
7ELYSEE HOMES
VILVATTOM, Thrissur
SINDHUJA REGENCY
AYYANTHOLE, Thrissur
Promised date
25 Feb 2027
no date change on file
30 Apr 2028
no date change on file
Physical %
0%
filed 11 Oct 2023
65%
filed 12 Oct 2023
Booked %
0%
0 of 7
39%
16 of 41
Complaints
none on file
from the public complaints list
none on file
from the public complaints list
Last QPR
never filed
no quarterly update on file
Q2 2026
filed 07 Oct 2026 · -34d ago · Current

Dash means missing on the snapshot. Status is derived from filed dates. Check rera.kerala.gov.in.