Same district, same year — promised date, physical %, booked %, complaints, last QPR. As filed. Not a ranking.

Snapshot 12 Oct 2026. Check rera.kerala.gov.in.

Palakkad · 2023 · K-RERA/PRJ/PKD/088/2023

Palakkad · 2023 · K-RERA/PRJ/PKD/016/2023

Same cohort: Palakkad · 2023.

As filed
V3 VIVAREAOverdue
Project
CASA CENTRAL
SHORANUR I, Palakkad
V3 VIVAREA
CHERPULACHERRY, Palakkad
Promised date
31 Jan 2025
19 months past promised date
31 Dec 2025
8 months past promised date
Physical %
67%
not filed
70%
filed 27 Oct 2023
Booked %
0%
0 of 59
79%
15 of 19
Complaints
none on file
from the public complaints list
none on file
from the public complaints list
Last QPR
Q1 2026
filed 10 Aug 2026 · 24d ago · Current
Q2 2026
filed 07 Oct 2026 · -34d ago · Current

Dash means missing on the snapshot. Status is derived from filed dates. Check rera.kerala.gov.in.