Same district, same year — promised date, physical %, booked %, complaints, last QPR. As filed. Not a ranking.
Snapshot 12 Oct 2026. Check rera.kerala.gov.in.
Palakkad · 2023 · K-RERA/PRJ/PKD/088/2023
Palakkad · 2023 · K-RERA/PRJ/PKD/081/2023
Same cohort: Palakkad · 2023.
Project
CASA CENTRAL
SHORANUR I, Palakkad
STHIRA AAVAS
PIRIYARI, Palakkad
Promised date
31 Jan 2025
19 months past promised date
19 Nov 2027
no date change on file
Physical %
67%
not filed
66%
not filed
Booked %
0%
0 of 59
75%
6 of 8
Complaints
none on file
from the public complaints list
none on file
from the public complaints list
Last QPR
Q1 2026
filed 10 Aug 2026 · 24d ago · Current
Q2 2026
filed 05 Oct 2026 · -32d ago · Current
Dash means missing on the snapshot. Status is derived from filed dates. Check rera.kerala.gov.in.