Same district, same year — promised date, physical %, booked %, complaints, last QPR. As filed. Not a ranking.
Snapshot 12 Oct 2026. Check rera.kerala.gov.in.
Palakkad · 2023 · K-RERA/PRJ/PKD/088/2023
Project
CASA CENTRAL
SHORANUR I, Palakkad
—
pick a project
Promised date
31 Jan 2025
19 months past promised date
—
Physical %
67%
not filed
—
Booked %
0%
0 of 59
—
Complaints
none on file
from the public complaints list
—
Last QPR
Q1 2026
filed 10 Aug 2026 · 24d ago · Current
—
Dash means missing on the snapshot. Status is derived from filed dates. Check rera.kerala.gov.in.
Same district, same year · Palakkad · 2023
DIVINE HOMESK-RERA/PRJ/PKD/002/2023STHIRA AAVASK-RERA/PRJ/PKD/081/2023OMG SILVERCREST VILLASK-RERA/PRJ/PKD/012/2023OMG GRANDEUR VILLASK-RERA/PRJ/PKD/038/2023SUKRUTHA LIVINGK-RERA/PRJ/PKD/027/2023V3 VIVAREAK-RERA/PRJ/PKD/016/2023V3 ECO VILLAGE 2K-RERA/PRJ/PKD/075/2023Neamath BrookfieldK-RERA/PRJ/PKD/052/2023