Same district, same year — promised date, physical %, booked %, complaints, last QPR. As filed. Not a ranking.
Snapshot 12 Oct 2026. Check rera.kerala.gov.in.
Thiruvananthapuram · 2023 · K-RERA/PRJ/TVM/111/2023
Thiruvananthapuram · 2023 · K-RERA/PRJ/TVM/026/2023
Same cohort: Thiruvananthapuram · 2023.
Project
OCEAN PEARL
THIRUVALLAM, Thiruvananthapuram
USHAKIRAN
NEMOM, Thiruvananthapuram
Promised date
31 Mar 2024
30 months past promised date
30 Apr 2024
29 months past promised date
Physical %
—
not filed
—
not filed
Booked %
100%
18 of 13
30%
13 of 44
Complaints
none on file
from the public complaints list
4
4 final orders
Last QPR
never filed
no quarterly update on file
never filed
no quarterly update on file
Dash means missing on the snapshot. Status is derived from filed dates. Check rera.kerala.gov.in.