Palakkad · 2023 · K-RERA/PRJ/PKD/071/2023
Palakkad · 2023 · K-RERA/PRJ/PKD/012/2023
Same cohort: Palakkad · 2023.
Project
SA CHARIOT
PALAKKAD-2, Palakkad
OMG SILVERCREST VILLAS
MARUTHUROAD, Palakkad
Promised date
21 Aug 2025
no date change on file
25 Dec 2027
no date change on file
Physical %
100%
filed 14 Oct 2023
71%
not filed
Booked %
100%
16 of 16
77%
24 of 31
Complaints
none on file
from the public complaints list
none on file
from the public complaints list
Last QPR
N/A
closed on the register — QPR not expected
Q2 2026
filed 05 Oct 2026 · -32d ago · Current
Dash means missing on the snapshot. Status is derived from filed dates. Check rera.kerala.gov.in.