Same district, same year — promised date, physical %, booked %, complaints, last QPR. As filed. Not a ranking.

Snapshot 12 Oct 2026. Check rera.kerala.gov.in.

Ernakulam · 2024 · K-RERA/PRJ/ERN/008/2024

Ernakulam · 2024 · K-RERA/PRJ/ERN/042/2024

Same cohort: Ernakulam · 2024.

As filed
SANTHI MELROSERegularised
Project
SANTHI MELROSE
MARADU, Ernakulam
RABBIT HABITAT
THIRUVANIYOOR, Ernakulam
Promised date
22 Mar 2023
no date change on file
30 Mar 2027
no date change on file
Physical %
0%
filed 17 Oct 2023
5%
not filed
Booked %
67%
8 of 12
0%
0 of 10
Complaints
3
no final order on file
none on file
from the public complaints list
Last QPR
N/A
closed on the register — QPR not expected
Q2 2026
filed 06 Oct 2026 · -33d ago · Current

Dash means missing on the snapshot. Status is derived from filed dates. Check rera.kerala.gov.in.