Same district, same year — promised date, physical %, booked %, complaints, last QPR. As filed. Not a ranking.

Snapshot 12 Oct 2026. Check rera.kerala.gov.in.

Thrissur · 2022 · K-RERA/PRJ/TSR/194/2022

Thrissur · 2022 · K-RERA/PRJ/TSR/167/2022

Same cohort: Thrissur · 2022.

As filed
AUREX LIARDCompleted
Project
AUREX LIARD
KILLANNUR, Thrissur
Ambalath Ayesha Homes
GURUVAYUR, Thrissur
Promised date
30 Nov 2026
no date change on file
04 Dec 2020
no date change on file
Physical %
100%
filed 28 Jun 2023
100%
not filed
Booked %
90%
28 of 31
0%
0 of 24
Complaints
none on file
from the public complaints list
none on file
from the public complaints list
Last QPR
N/A
closed on the register — QPR not expected
N/A
closed on the register — QPR not expected

Dash means missing on the snapshot. Status is derived from filed dates. Check rera.kerala.gov.in.