Same district, same year — promised date, physical %, booked %, complaints, last QPR. As filed. Not a ranking.
Snapshot 12 Oct 2026. Check rera.kerala.gov.in.
Kottayam · 2023 · K-RERA/PRJ/KTM/034/2023
Kottayam · 2023 · K-RERA/PRJ/KTM/095/2023
Same cohort: Kottayam · 2023.
Project
NTP LORDS VALLEY - Phase 6
PERUMBAYIKKADU, Kottayam
SKYLINE CENTRAL AVENUE
VIJAYAPURAM, Kottayam
Promised date
31 Dec 2025
8 months past promised date
30 Jun 2024
no date change on file
Physical %
0%
not filed
100%
not filed
Booked %
0%
0 of 14
28%
13 of 47
Complaints
none on file
from the public complaints list
none on file
from the public complaints list
Last QPR
Q2 2025
filed 17 Oct 2025 · 321d ago · Stale
N/A
closed on the register — QPR not expected
Dash means missing on the snapshot. Status is derived from filed dates. Check rera.kerala.gov.in.