Same district, same year — promised date, physical %, booked %, complaints, last QPR. As filed. Not a ranking.
Snapshot 12 Oct 2026. Check rera.kerala.gov.in.
Kottayam · 2022 · K-RERA/PRJ/KTM/198/2022
Kottayam · 2022 · K-RERA/PRJ/008/2022
Same cohort: Kottayam · 2022.
Project
CONFIDENT CYGNUS BLOCK B
MUTTAMBALAM, Kottayam
ORCHID PARK
VIJAYAPURAM, Kottayam
Promised date
15 Mar 2028
no date change on file
30 Sept 2022
48 months past promised date
Physical %
82%
filed 07 Oct 2023
98%
not filed
Booked %
69%
61 of 88
65%
80 of 124
Complaints
none on file
from the public complaints list
67
30 final orders
Last QPR
Q2 2026
filed 07 Oct 2026 · -34d ago · Current
Q1 2025
filed 19 Jul 2025 · 411d ago · Stale