Same district, same year — promised date, physical %, booked %, complaints, last QPR. As filed. Not a ranking.
Snapshot 12 Oct 2026. Check rera.kerala.gov.in.
Palakkad · 2023 · K-RERA/PRJ/PKD/075/2023
Palakkad · 2023 · K-RERA/PRJ/PKD/016/2023
Same cohort: Palakkad · 2023.
Project
V3 ECO VILLAGE 2
OTTAPALAM I, Palakkad
V3 VIVAREA
CHERPULACHERRY, Palakkad
Promised date
30 Apr 2027
no date change on file
31 Dec 2025
8 months past promised date
Physical %
27%
filed 27 Oct 2023
70%
filed 27 Oct 2023
Booked %
66%
19 of 29
79%
15 of 19
Complaints
1
no final order on file
none on file
from the public complaints list
Last QPR
Q2 2026
filed 07 Oct 2026 · -34d ago · Current
Q2 2026
filed 07 Oct 2026 · -34d ago · Current
Dash means missing on the snapshot. Status is derived from filed dates. Check rera.kerala.gov.in.