Same district, same year — promised date, physical %, booked %, complaints, last QPR. As filed. Not a ranking.

Snapshot 12 Oct 2026. Check rera.kerala.gov.in.

Ernakulam · 2022 · K-RERA/PRJ/ERN/150/2022

Ernakulam · 2022 · K-RERA/PRJ/ERN/021/2022

Same cohort: Ernakulam · 2022.

As filed
SKYLINE ZENCompleted
INFRA PROXIMCompleted
Project
SKYLINE ZEN
EDAPPALLY SOUTH, Ernakulam
INFRA PROXIM
EDAPPALLY NORTH, Ernakulam
Promised date
14 Oct 2027
no date change on file
01 Jul 2022
no date change on file
Physical %
100%
not filed
100%
not filed
Booked %
100%
44 of 44
100%
31 of 31
Complaints
none on file
from the public complaints list
5
1 final order
Last QPR
N/A
closed on the register — QPR not expected
N/A
closed on the register — QPR not expected

Dash means missing on the snapshot. Status is derived from filed dates. Check rera.kerala.gov.in.