Skip to main content
Enthayi?
K-RERA
← Projects

Compare

Same district, same year — promised date, physical %, booked %, complaints, last QPR. As filed. Not a ranking.

Snapshot 12 Oct 2026. Check rera.kerala.gov.in.

Idukki · 2022 · K-RERA/PRJ/IDK/203/2022

Idukki · 2022 · K-RERA/PRJ/IDK/015/2022

Same cohort: Idukki · 2022.

As filed
Hill HomesCompleted
Project
Hill Homes
ELAPPARA, Idukki
Winterlake Kuttikanam
ELAPPARA, Idukki
Promised date
01 Apr 2026
no date change on file
15 Dec 2025
9 months past promised date
Physical %
100%
filed 10 Oct 2023
85%
filed 13 Jul 2023
Booked %
83%
25 of 30
66%
25 of 38
Complaints
none on file
from the public complaints list
none on file
from the public complaints list
Last QPR
N/A
closed on the register — QPR not expected
Q2 2025
filed 07 Oct 2025 · 331d ago · Stale

Dash means missing on the snapshot. Status is derived from filed dates. Check rera.kerala.gov.in.