Same district, same year — promised date, physical %, booked %, complaints, last QPR. As filed. Not a ranking.

Snapshot 12 Oct 2026. Check rera.kerala.gov.in.

Thrissur · 2022 · K-RERA/PRJ/TSR/179/2022

Thrissur · 2022 · K-RERA/PRJ/012/2022

Same cohort: Thrissur · 2022.

As filed
Project
ASSET WINSIDE
KILLANNUR, Thrissur
NANDANAM HABITAT
IRINGAPRAM, Thrissur
Promised date
30 Mar 2027
no date change on file
30 Jun 2023
no date change on file
Physical %
60%
filed 06 Oct 2023
100%
filed 20 Jul 2023
Booked %
85%
61 of 72
0%
0 of 58
Complaints
none on file
from the public complaints list
5
no final order on file
Last QPR
Q2 2026
filed 06 Oct 2026 · -33d ago · Current
N/A
closed on the register — QPR not expected

Dash means missing on the snapshot. Status is derived from filed dates. Check rera.kerala.gov.in.