Same district, same year — promised date, physical %, booked %, complaints, last QPR. As filed. Not a ranking.

Snapshot 12 Oct 2026. Check rera.kerala.gov.in.

Thrissur · 2022 · K-RERA/PRJ/TSR/179/2022

Thrissur · 2022 · K-RERA/PRJ/TSR/177/2022

Same cohort: Thrissur · 2022.

As filed
GOVIND SUITECompleted
Project
ASSET WINSIDE
KILLANNUR, Thrissur
GOVIND SUITE
AYYANTHOLE, Thrissur
Promised date
30 Mar 2027
no date change on file
15 Feb 2027
no date change on file
Physical %
60%
filed 06 Oct 2023
100%
not filed
Booked %
85%
61 of 72
44%
7 of 16
Complaints
none on file
from the public complaints list
none on file
from the public complaints list
Last QPR
Q2 2026
filed 06 Oct 2026 · -33d ago · Current
N/A
closed on the register — QPR not expected

Dash means missing on the snapshot. Status is derived from filed dates. Check rera.kerala.gov.in.