Same district, same year — promised date, physical %, booked %, complaints, last QPR. As filed. Not a ranking.

Snapshot 12 Oct 2026. Check rera.kerala.gov.in.

Thrissur · 2022 · K-RERA/PRJ/TSR/183/2022

Thrissur · 2022 · K-RERA/PRJ/TSR/058/2022

Same cohort: Thrissur · 2022.

As filed
FIFTH AVENUECompleted
Project
VISHRAAM LIMELITE
VIYYUR, Thrissur
FIFTH AVENUE
OLLUR, Thrissur
Promised date
29 Feb 2028
no date change on file
31 Dec 2025
no date change on file
Physical %
63%
filed 07 Oct 2023
100%
filed 01 Oct 2023
Booked %
72%
59 of 82
29%
4 of 14
Complaints
none on file
from the public complaints list
none on file
from the public complaints list
Last QPR
Q2 2026
filed 07 Oct 2026 · -34d ago · Current
N/A
closed on the register — QPR not expected

Dash means missing on the snapshot. Status is derived from filed dates. Check rera.kerala.gov.in.