Same district, same year — promised date, physical %, booked %, complaints, last QPR. As filed. Not a ranking.

Snapshot 12 Oct 2026. Check rera.kerala.gov.in.

Ernakulam · 2023 · K-RERA/PRJ/ERN/049/2023

Ernakulam · 2023 · K-RERA/PRJ/ERN/073/2023

Same cohort: Ernakulam · 2023.

As filed
GALAXY OXTONCompleted
VARMA FICUSOn Track
Project
GALAXY OXTON
ELAMKULAM, Ernakulam
VARMA FICUS
EDAPPALLY SOUTH, Ernakulam
Promised date
29 May 2020
no date change on file
30 Oct 2028
no date change on file
Physical %
100%
not filed
90%
filed 04 Dec 2023
Booked %
97%
70 of 72
94%
31 of 33
Complaints
6
4 final orders
none on file
from the public complaints list
Last QPR
N/A
closed on the register — QPR not expected
Q2 2026
filed 07 Oct 2026 · -34d ago · Current

Dash means missing on the snapshot. Status is derived from filed dates. Check rera.kerala.gov.in.