Same district, same year — promised date, physical %, booked %, complaints, last QPR. As filed. Not a ranking.
Snapshot 12 Oct 2026. Check rera.kerala.gov.in.
Ernakulam · 2023 · K-RERA/PRJ/ERN/049/2023
Ernakulam · 2023 · K-RERA/PRJ/ERN/078/2023
Same cohort: Ernakulam · 2023.
Project
GALAXY OXTON
ELAMKULAM, Ernakulam
SPICE VALLEY
KUNNATHUNAD, Ernakulam
Promised date
29 May 2020
no date change on file
25 Dec 2025
8 months past promised date
Physical %
100%
not filed
82%
not filed
Booked %
97%
70 of 72
93%
13 of 14
Complaints
6
4 final orders
none on file
from the public complaints list
Last QPR
N/A
closed on the register — QPR not expected
Q2 2025
filed 07 Oct 2025 · 331d ago · Stale
Dash means missing on the snapshot. Status is derived from filed dates. Check rera.kerala.gov.in.