Same district, same year — promised date, physical %, booked %, complaints, last QPR. As filed. Not a ranking.

Snapshot 12 Oct 2026. Check rera.kerala.gov.in.

Kottayam · 2022 · K-RERA/PRJ/KTM/146/2022

Kottayam · 2022 · K-RERA/PRJ/008/2022

Same cohort: Kottayam · 2022.

As filed
GRAND MAPLECompleted
Project
GRAND MAPLE
KAIPPUZHA, Kottayam
ORCHID PARK
VIJAYAPURAM, Kottayam
Promised date
27 Feb 2019
no date change on file
30 Sept 2022
48 months past promised date
Physical %
100%
not filed
98%
not filed
Booked %
0%
0 of 73
65%
80 of 124
Complaints
2
2 final orders
67
30 final orders
Last QPR
N/A
closed on the register — QPR not expected
Q1 2025
filed 19 Jul 2025 · 411d ago · Stale

Dash means missing on the snapshot. Status is derived from filed dates. Check rera.kerala.gov.in.