Same district, same year — promised date, physical %, booked %, complaints, last QPR. As filed. Not a ranking.

Snapshot 12 Oct 2026. Check rera.kerala.gov.in.

Palakkad · 2022 · K-RERA/PRJ/PKD/164/2022

Palakkad · 2022 · K-RERA/PRJ/PKD/009/2022

Same cohort: Palakkad · 2022.

As filed
Project
V3 PRAKRITI
LAKKIDIPERUR II, Palakkad
Hanco Fort Heights
PALAKKAD-3, Palakkad
Promised date
31 Dec 2025
8 months past promised date
30 Mar 2030
no date change on file
Physical %
90%
filed 27 Oct 2023
68%
filed 30 Oct 2023
Booked %
77%
10 of 13
25%
20 of 80
Complaints
1
no final order on file
none on file
from the public complaints list
Last QPR
Q2 2026
filed 07 Oct 2026 · -34d ago · Current
Q2 2026
filed 06 Oct 2026 · -33d ago · Current

Dash means missing on the snapshot. Status is derived from filed dates. Check rera.kerala.gov.in.