Same district, same year — promised date, physical %, booked %, complaints, last QPR. As filed. Not a ranking.
Snapshot 12 Oct 2026. Check rera.kerala.gov.in.
Ernakulam · 2022 · K-RERA/PRJ/ERN/103/2022
Ernakulam · 2022 · K-RERA/PRJ/ERN/056/2022
Same cohort: Ernakulam · 2022.
Project
Janani Project - Ponjasserry
ARAKAPADY, Ernakulam
Tulsi Majestic Court
ERNAKULAM, Ernakulam
Promised date
05 Nov 2022
no date change on file
31 Dec 2022
no date change on file
Physical %
100%
filed 05 Aug 2023
100%
not filed
Booked %
0%
0 of 74
0%
0 of 14
Complaints
none on file
from the public complaints list
none on file
from the public complaints list
Last QPR
N/A
closed on the register — QPR not expected
N/A
closed on the register — QPR not expected
Dash means missing on the snapshot. Status is derived from filed dates. Check rera.kerala.gov.in.