Skip to main content
Enthayi?
K-RERA
← Projects

Compare

Same district, same year — promised date, physical %, booked %, complaints, last QPR. As filed. Not a ranking.

Snapshot 12 Oct 2026. Check rera.kerala.gov.in.

Kottayam · 2022 · K-RERA/PRJ/KTM/137/2022

Kottayam · 2022 · K-RERA/PRJ/KTM/146/2022

Same cohort: Kottayam · 2022.

As filed
ASSET BELFORDCompleted
GRAND MAPLECompleted
Project
ASSET BELFORD
PUTHUPPALLY KOTTAYAM, Kottayam
GRAND MAPLE
KAIPPUZHA, Kottayam
Promised date
31 Mar 2025
no date change on file
27 Feb 2019
no date change on file
Physical %
100%
filed 06 Oct 2023
100%
not filed
Booked %
100%
18 of 18
0%
0 of 73
Complaints
none on file
from the public complaints list
2
2 final orders
Last QPR
N/A
closed on the register — QPR not expected
N/A
closed on the register — QPR not expected

Dash means missing on the snapshot. Status is derived from filed dates. Check rera.kerala.gov.in.