Same district, same year — promised date, physical %, booked %, complaints, last QPR. As filed. Not a ranking.

Snapshot 12 Oct 2026. Check rera.kerala.gov.in.

Kottayam · 2022 · K-RERA/PRJ/KTM/137/2022

Kottayam · 2022 · K-RERA/PRJ/KTM/048/2022

Same cohort: Kottayam · 2022.

As filed
ASSET BELFORDCompleted
Project
ASSET BELFORD
PUTHUPPALLY KOTTAYAM, Kottayam
NTP LORDS VALLEY
PERUMBAYIKKADU, Kottayam
Promised date
31 Mar 2025
no date change on file
31 Jul 2023
38 months past promised date
Physical %
100%
filed 06 Oct 2023
93%
not filed
Booked %
100%
18 of 18
100%
43 of 41
Complaints
none on file
from the public complaints list
8
8 final orders
Last QPR
N/A
closed on the register — QPR not expected
Q1 2025
filed 03 Jul 2025 · 427d ago · Stale

Dash means missing on the snapshot. Status is derived from filed dates. Check rera.kerala.gov.in.