Ernakulam · 2022 · K-RERA/PRJ/ERN/055/2022

Ernakulam · 2022 · K-RERA/PRJ/ERN/021/2022

Same cohort: Ernakulam · 2022.

As filed
Tulsi NestCompleted
INFRA PROXIMCompleted
Project
Tulsi Nest
THRIKKAKARA NORTH, Ernakulam
INFRA PROXIM
EDAPPALLY NORTH, Ernakulam
Promised date
30 Jun 2022
no date change on file
01 Jul 2022
no date change on file
Physical %
100%
not filed
100%
not filed
Booked %
100%
36 of 36
100%
31 of 31
Complaints
2
2 final orders
5
1 final order
Last QPR
N/A
closed on the register — QPR not expected
N/A
closed on the register — QPR not expected

Dash means missing on the snapshot. Status is derived from filed dates. Check rera.kerala.gov.in.