Same district, same year — promised date, physical %, booked %, complaints, last QPR. As filed. Not a ranking.
Snapshot 12 Oct 2026. Check rera.kerala.gov.in.
Thrissur · 2022 · K-RERA/PRJ/TSR/078/2022
Thrissur · 2022 · K-RERA/PRJ/TSR/091/2022
Same cohort: Thrissur · 2022.
Project
ELITE PARADIZA
KUTTOOR THRISSUR, Thrissur
SOWPARNIKA SUDARSHANAM
GURUVAYUR, Thrissur
Promised date
31 Mar 2026
no date change on file
31 Dec 2022
no date change on file
Physical %
100%
not filed
100%
filed 07 Jul 2023
Booked %
89%
16 of 18
98%
149 of 152
Complaints
none on file
from the public complaints list
none on file
from the public complaints list
Last QPR
N/A
closed on the register — QPR not expected
N/A
closed on the register — QPR not expected
Dash means missing on the snapshot. Status is derived from filed dates. Check rera.kerala.gov.in.