Snapshot 12 Oct 2026. Check rera.kerala.gov.in.

Ernakulam · 2022 · K-RERA/PRJ/ERN/172/2022

Ernakulam · 2022 · K-RERA/PRJ/ERN/003/2022

Same cohort: Ernakulam · 2022.

As filed
SKY AT 11On Track
ANTA - MARVELCompleted
Project
SKY AT 11
MARADU, Ernakulam
ANTA - MARVEL
MARADU, Ernakulam
Promised date
30 Apr 2027
no date change on file
31 Dec 2019
no date change on file
Physical %
48%
filed 28 Dec 2023
100%
not filed
Booked %
6%
1 of 18
100%
52 of 52
Complaints
2
1 final order
9
1 final order
Last QPR
Q4 2025
filed 09 Jan 2026 · 237d ago · Stale
N/A
closed on the register — QPR not expected