Same district, same year — promised date, physical %, booked %, complaints, last QPR. As filed. Not a ranking.

Snapshot 12 Oct 2026. Check rera.kerala.gov.in.

Kannur · 2021 · K-RERA/PRJ/198/2021

Kannur · 2021 · K-RERA/PRJ/KNR/010/2021

Same cohort: Kannur · 2021.

As filed
Sailors CoveOn Track
ASSET CHAMBERCompleted
Project
Sailors Cove
CHIRAKKAL, Kannur
ASSET CHAMBER
ELAYAVOOR, Kannur
Promised date
30 Oct 2026
no date change on file
30 Jun 2025
no date change on file
Physical %
—
not filed
100%
filed 06 Oct 2023
Booked %
30%
64 of 211
100%
82 of 82
Complaints
none on file
from the public complaints list
none on file
from the public complaints list
Last QPR
never filed
no quarterly update on file
N/A
closed on the register — QPR not expected

Dash means missing on the snapshot. Status is derived from filed dates. Check rera.kerala.gov.in.