Same district, same year — promised date, physical %, booked %, complaints, last QPR. As filed. Not a ranking.

Snapshot 12 Oct 2026. Check rera.kerala.gov.in.

Thiruvananthapuram · 2022 · K-RERA/PRJ/TVM/067/2022

Thiruvananthapuram · 2022 · K-RERA/PRJ/TVM/057/2022

Same cohort: Thiruvananthapuram · 2022.

As filed
SFS AMBERCompleted
Project
SFS AMBER
KUDAPPANAKUNNU, Thiruvananthapuram
Aroma By the Cliff
KOWDIAR, Thiruvananthapuram
Promised date
27 Feb 2027
no date change on file
31 Dec 2025
8 months past promised date
Physical %
100%
filed 07 Oct 2023
95%
not filed
Booked %
88%
63 of 72
76%
39 of 51
Complaints
none on file
from the public complaints list
1
no final order on file
Last QPR
N/A
closed on the register — QPR not expected
Q2 2025
filed 10 Oct 2025 · 328d ago · Stale

Dash means missing on the snapshot. Status is derived from filed dates. Check rera.kerala.gov.in.