Same district, same year — promised date, physical %, booked %, complaints, last QPR. As filed. Not a ranking.

Snapshot 12 Oct 2026. Check rera.kerala.gov.in.

Ernakulam · 2021 · K-RERA/PRJ/201/2021

Ernakulam · 2021 · K-RERA/PRJ/114/2021

Same cohort: Ernakulam · 2021.

As filed
ERA PRIMEOverdue
Project
ERA PRIME
MANAKUNNAM, Ernakulam
DREAMFLOWER LA-CASITA
VAZHAKKALA, Ernakulam
Promised date
30 Jun 2023
39 months past promised date
31 Jan 2024
no date change on file
Physical %
96%
filed 28 Dec 2023
100%
filed 14 Jan 2023
Booked %
94%
17 of 18
100%
40 of 40
Complaints
7
6 final orders
none on file
from the public complaints list
Last QPR
Q1 2025
filed 07 Jul 2025 · 423d ago · Stale
N/A
closed on the register — QPR not expected

Dash means missing on the snapshot. Status is derived from filed dates. Check rera.kerala.gov.in.