Same district, same year — promised date, physical %, booked %, complaints, last QPR. As filed. Not a ranking.
Snapshot 12 Oct 2026. Check rera.kerala.gov.in.
Thrissur · 2021 · K-RERA/PRJ/TSR/074/2021
Thrissur · 2021 · K-RERA/PRJ/TSR/002/2021
Same cohort: Thrissur · 2021.
Project
MULBERRY HOMES-PAM RIDGE
KUTTOOR THRISSUR, Thrissur
SOBHA METROPOLIS-PHASE 1
OLLUR, Thrissur
Promised date
27 Jul 2024
26 months past promised date
30 Apr 2027
no date change on file
Physical %
0%
filed 07 Jul 2023
81%
filed 07 Oct 2023
Booked %
0%
0 of 18
99%
252 of 254
Complaints
none on file
from the public complaints list
none on file
from the public complaints list
Last QPR
Q1 2025
filed 07 Jul 2025 · 423d ago · Stale
Q2 2026
filed 07 Oct 2026 · -34d ago · Current
Dash means missing on the snapshot. Status is derived from filed dates. Check rera.kerala.gov.in.