Thrissur · 2021 · K-RERA/PRJ/TSR/074/2021
Thrissur · 2021 · K-RERA/PRJ/016/2021
Same cohort: Thrissur · 2021.
Project
MULBERRY HOMES-PAM RIDGE
KUTTOOR THRISSUR, Thrissur
SREEPAVANAPURI APARTMENT
IRINGAPRAM, Thrissur
Promised date
27 Jul 2024
26 months past promised date
30 May 2023
no date change on file
Physical %
0%
filed 07 Jul 2023
100%
not filed
Booked %
0%
0 of 18
0%
0 of 84
Complaints
none on file
from the public complaints list
none on file
from the public complaints list
Last QPR
Q1 2025
filed 07 Jul 2025 · 423d ago · Stale
N/A
closed on the register — QPR not expected