Same district, same year — promised date, physical %, booked %, complaints, last QPR. As filed. Not a ranking.
Snapshot 12 Oct 2026. Check rera.kerala.gov.in.
Thrissur · 2020 · K-RERA/PRJ/161/2020
Thrissur · 2020 · K-RERA/PRJ/010/2020
Same cohort: Thrissur · 2020.
Project
KRISHNA HOMES AMBADI RESIDENCY
THRISSUR, Thrissur
FORUS AZALEA
CHEMBUKAVU, Thrissur
Promised date
31 Dec 2023
33 months past promised date
01 May 2023
no date change on file
Physical %
88%
not filed
100%
filed 23 Jun 2023
Booked %
100%
18 of 18
88%
14 of 16
Complaints
none on file
from the public complaints list
none on file
from the public complaints list
Last QPR
Q2 2026
filed 06 Oct 2026 · -33d ago · Current
N/A
closed on the register — QPR not expected
Dash means missing on the snapshot. Status is derived from filed dates. Check rera.kerala.gov.in.