← Projects
Compare
Same district, same year — promised date, physical %, booked %, complaints, last QPR. As filed. Not a ranking.
Snapshot 12 Oct 2026. Check rera.kerala.gov.in.
Palakkad · 2021 · K-RERA/PRJ/PKD/052/2021
Project
V3 FELIZ CASA
PIRIYARI, Palakkad
—
pick a project
Promised date
28 Feb 2025
no date change on file
—
Physical %
100%
filed 27 Oct 2023
—
Booked %
100%
14 of 14
—
Complaints
none on file
from the public complaints list
—
Last QPR
N/A
closed on the register — QPR not expected
—
Dash means missing on the snapshot. Status is derived from filed dates. Check rera.kerala.gov.in.
Same district, same year · Palakkad · 2021
OMG LIFESTYLES PHASE 3K-RERA/PRJ/056/2021OMG VIVANTE VILLAS PHASE -2K-RERA/PRJ/100/2021SAMRUDHI HOMESK-RERA/PRJ/107/2021VIOLET HOMESK-RERA/PRJ/116/2021VICTORIA REALTORS CHAITHRAM THIRD PHASEK-RERA/PRJ/105/2021VICTORIA REALTORS USHASK-RERA/PRJ/035/2021VICTORIA REALTORS ASHIRVAADK-RERA/PRJ/088/2021V3 AVONLEAK-RERA/PRJ/006/2021