Same district, same year — promised date, physical %, booked %, complaints, last QPR. As filed. Not a ranking.
Snapshot 12 Oct 2026. Check rera.kerala.gov.in.
Kollam · 2021 · K-RERA/PRJ/KLM/078/2021
Kollam · 2021 · K-RERA/PRJ/064/2021
Same cohort: Kollam · 2021.
Project
KCHELL RESIDENCY
SHAKTHIKULANGARA, Kollam
KSK MOUNT CASTLE
MELILA, Kollam
Promised date
06 Jun 2019
no date change on file
31 Dec 2022
no date change on file
Physical %
100%
not filed
100%
filed 10 Jan 2023
Booked %
44%
30 of 68
0%
0 of 6
Complaints
2
2 final orders
none on file
from the public complaints list
Last QPR
N/A
closed on the register — QPR not expected
N/A
closed on the register — QPR not expected
Dash means missing on the snapshot. Status is derived from filed dates. Check rera.kerala.gov.in.