Same district, same year — promised date, physical %, booked %, complaints, last QPR. As filed. Not a ranking.

Snapshot 12 Oct 2026. Check rera.kerala.gov.in.

Ernakulam · 2021 · K-RERA/PRJ/091/2021

Ernakulam · 2021 · K-RERA/PRJ/ERN/004/2021

Same cohort: Ernakulam · 2021.

Project
NUCLEUS HEYDAY VILLAS AND APARTMENTS
VAZHAKKALA, Ernakulam
NANMA EASTFORT
MARADY, Ernakulam
Promised date
30 Apr 2022
53 months past promised date
10 Dec 2025
no date change on file
Physical %
—
not filed
100%
not filed
Booked %
48%
15 of 31
98%
145 of 148
Complaints
1
1 final order
none on file
from the public complaints list
Last QPR
never filed
no quarterly update on file
N/A
closed on the register — QPR not expected

Dash means missing on the snapshot. Status is derived from filed dates. Check rera.kerala.gov.in.