Same district, same year — promised date, physical %, booked %, complaints, last QPR. As filed. Not a ranking.
Snapshot 12 Oct 2026. Check rera.kerala.gov.in.
Ernakulam · 2021 · K-RERA/PRJ/091/2021
Project
NUCLEUS HEYDAY VILLAS AND APARTMENTS
VAZHAKKALA, Ernakulam
—
pick a project
Promised date
30 Apr 2022
53 months past promised date
—
Physical %
—
not filed
—
Booked %
48%
15 of 31
—
Complaints
1
1 final order
—
Last QPR
never filed
no quarterly update on file
—
Dash means missing on the snapshot. Status is derived from filed dates. Check rera.kerala.gov.in.