Same district, same year — promised date, physical %, booked %, complaints, last QPR. As filed. Not a ranking.

Snapshot 12 Oct 2026. Check rera.kerala.gov.in.

Kollam · 2021 · K-RERA/PRJ/KLM/034/2021

Kollam · 2021 · K-RERA/PRJ/KLM/078/2021

Same cohort: Kollam · 2021.

As filed
Project
PUTRI BHOOMI
KOLLAM WEST, Kollam
KCHELL RESIDENCY
SHAKTHIKULANGARA, Kollam
Promised date
15 Jul 2023
38 months past promised date
06 Jun 2019
no date change on file
Physical %
0%
filed 31 Oct 2022
100%
not filed
Booked %
0%
0 of 17
44%
30 of 68
Complaints
none on file
from the public complaints list
2
2 final orders
Last QPR
never filed
no quarterly update on file
N/A
closed on the register — QPR not expected

Dash means missing on the snapshot. Status is derived from filed dates. Check rera.kerala.gov.in.