Same district, same year — promised date, physical %, booked %, complaints, last QPR. As filed. Not a ranking.

Snapshot 12 Oct 2026. Check rera.kerala.gov.in.

Ernakulam · 2021 · K-RERA/PRJ/080/2021

Ernakulam · 2021 · K-RERA/PRJ/007/2021

Same cohort: Ernakulam · 2021.

As filed
Project
BREEZY MEADOWS
NADAMA, Ernakulam
LOTUS NANDANAM
NADAMA, Ernakulam
Promised date
30 Dec 2024
20 months past promised date
31 Oct 2023
no date change on file
Physical %
50%
filed 07 Nov 2023
100%
filed 12 Oct 2023
Booked %
94%
15 of 16
100%
22 of 22
Complaints
2
no final order on file
none on file
from the public complaints list
Last QPR
Q1 2026
filed 10 Jul 2026 · 55d ago · Current
N/A
closed on the register — QPR not expected

Dash means missing on the snapshot. Status is derived from filed dates. Check rera.kerala.gov.in.